Types Of Estimates In Quantity Surveying
What is an Estimate?
An Estimate is what determines the probable cost of a
project, which can be a building, a car or it even can be small lightning bulb.
Types Of Estimates In Use
Types of Estimates can be divided based on how project is
quantified. Also the level of accuracy required will dictate which estimate is
suitable for a particular project.
Three broad types of estimates are listed below
Detailed Estimate
Assembly Estimate
Unit Estimate
Detailed Estimate
Detailed Estimate determines the quantity and cost of each
and every thing that is required for project.
Detailed estimating, also named as “Prime Cost”, “Bottoms
Up” or “Grass Roots” estimates. As name indicates, these estimates requires a
thorough and detailed analysis of all the tasks required to deliver a project
or product.
It is obvious that these types of estimates are costly to
produce because of the time and effort required. The accuracy however is the
best among all the estimates.
These types of estimate is done when all information is
available such as drawings, process sheets, planning etc. Each item is listed
on estimate work-up sheet. Project is broken down into deliverable. Each
deliverable has allocated time and cost.
After this WBS (work breakdown structure) is made which
ensures that each deliverable is placed in right time so that project is
completed in allocated time.
Following costs can be included in detailed estimate:
Labor
Material
Equipment
Insurance
Bonds
Overheads etc.
Assembly Estimate
An Assembly Estimate, rather than bidding for each
individual components of the project, The Estimator bids the components in
groups known as assemblies.
In order to fully understand what an assembly estimate is,
lets consider simple example of an lightning switch assembly.
Single Gang-Box
Single Pole Switch
Cover Plate
Two Wire Nuts
Gage Wire
Lets now see how assembly estimating works in civil
engineering.
Assembly method follows sequential approach defining how
building will be constructed. One advantage of assembly estimate that two
assemblies can be substituted in place of each other in order to quickly
determine cost difference of two assemblies.
Assembly estimate is not as accurate as detailed estimate
which makes it less costly too. An Assembly estimate is best when it is used as
a budgeting tool in the planning stages of a project because the accuracy of
the estimate is usually 15% +-.
Typical estimate of substructure and foundation estimate is
shown below
Unit Estimate
Unit estimates are prepared by by multiplying unit area of
the building by cost per unit area and then adjusting the price to compensate
for differences in building height, length of the building perimeter, and other
building components.
Unit estimates are sometimes refereed to as square-foot
estimates as most common area unit used is square foot. These types of
estimates are “educated guesses” as not much accuracy is achieved.
Unit estimates are common when there is uncertainty about the amount of work to be
done.
Unit estimate has two parts
price per unit of work involved for different phases of
project
Quantification of actual work which is completed on site.
Comments
Post a Comment